Pause new data center and substation approvals until Loudoun has a plan

Last changed
The ask

On Nov. 17, 2026 the Board of Supervisors should adopt the pause resolution it directed on Sept. 15, and keep it in place until the Phase 2 data center rules are adopted.

What data centers pay, and what they need

Data centers pay a lot of Loudoun's bills. In the FY 2027 adopted budget, real property and computer equipment taxes from data centers come to about $1.3 billion, roughly 40 percent of General Fund revenue.[4] That money matters. A pause does not touch any data center already built.

Every data center the county approves needs power. That power comes through substations and transmission lines. Loudoun has approved data centers one application at a time for 25 years, and it still has no plan for how many more it can power or where the lines to serve them will go.

What the Board has done

On Sept. 15, 2026 the Board directed staff, 7-1-0-1, to prepare a resolution pausing its consideration of legislative data center and substation applications for up to 12 months from the date each one first goes to the Planning Commission. The purpose, in the Board's motion, is "for the Board of Supervisors to apply Phase 2 of the Data Centers Standards and Locations ZOAM and CPAM to the application." The pause is effective Sept. 15 and does not make any application inactive. A second motion, also 7-1-0-1, lets the Board take up an application during the pause if it involves a grid reliability substation or its statutory deadline is about to run out.[2]

The County Attorney advised that a blanket moratorium is not legal in Virginia, and that the Board can defer its own final votes within the state's 12-month deadline. The pause covers final votes only. Applications can still be filed and reviewed by the Planning Commission.[1]

The same night, the Board denied the Tech Park at Dulles substation, 6-3. Its written findings say: "The electrical grid in Loudoun County is severely strained," and a new direct-connect substation "will exacerbate the problem by promoting development of new high wattage users and causing off site impacts of new high voltage transmission lines within the County."[2]

What the SCC said

The SCC reached the same point in its April 9, 2026 Golden to Mars order. It wrote that as data centers concentrate in one area, there may come a point where no reasonable transmission route is left.[5] The county decides how many data centers it approves. The SCC then decides where the lines go.

Phase 2 is the county's next set of data center rules: compatibility and siting, substation policy, on-site power generation, noise and building height. The county expects to finish it in 2027.[3] A pause means the Board decides the next applications under those rules, not under the old ones while the new ones are still being written.

What the pause does not do

It does not reach administrative applications, such as site plans. That includes the projects still moving under the 2025 grandfathering resolution. See Grandfathering.

What happens next

The vote was set for Oct. 20. At the County Attorney's request, Chair Phyllis Randall moved it to the Board's Nov. 17, 2026 business meeting.[6] Email the Board at bos@loudoun.gov before then.

Coming up on this issue

Full Calendar →
NOV17VoteBoard of Supervisors takes up the data center and substation pause resolutionBoard of Supervisors · 4:00 pm

Across the site

Tagged The pause
UpdatesAll 2 →
GOLDEN Board of Supervisors Vote TONIGHT!Newsletter · Sep 1, 2026Tonight: Vantage Data Center Town Hall. Next Week: Town Hall with the Lt. Governor. Much More.Newsletter · Aug 24, 2026
CoverageAll 32 →
Lawmakers Punt On Stripping Approvals From 15 Projects In Data Center AlleyBisnow · Oct 7, 2026Loudoun Board Prepares for Big Data Center Changes as Lawsuit Threats LoomLoudoun Now · Oct 5, 2026Virginia’s Loudoun County board votes to pause new data center applicationsData Center Dynamics · Sep 18, 2026
Data center taxes as a share of Loudoun's General Fund, FY 2027Data as of Oct 8, 2026JLARC Report 598: Data Centers in VirginiaData as of Dec 9, 2024
TrackerAll 8 →
AWS on the former GW campus (Bridgefield Tech Center)Active · Data centerDominion and NextEra mergerActive · OtherGolden SubstationActive · Substation

Sources

  1. [1]Board approves process that could pause legislative data center and substation applications. Loudoun County. Sep 17, 2026.
  2. [2]Revised Action Report, Board of Supervisors Business Meeting of Sept. 15, 2026, Items 14.j and 14.l. Loudoun County. Sep 17, 2026.
  3. [3]Phase 2: Data Center Standards and Locations. Loudoun County. Oct 8, 2026.
  4. [4]FY 2027 Adopted Budget, General Fund Revenue. Loudoun County. Jul 1, 2026.
  5. [5]Order, Case No. PUR-2025-00056 (Golden to Mars). Virginia State Corporation Commission. Apr 9, 2026. PUR-2025-00056
  6. [6]Loudoun County board defers vote on data center pause. Loudoun Times-Mirror. Oct 20, 2026.
Latest update on The pause
GOLDEN Board of Supervisors Vote TONIGHT!Newsletter · Sep 1, 2026Read the Update →