Built · Data center

Vantage VA2, Sterling

A Vantage Data Centers campus on Glenn Drive in Sterling that runs on on-site gas turbines because the grid cannot yet serve it. Vantage says it does not expect a grid connection until 2040.

Last changed
Sterling District3 proceedings
Type
Data center campus powered by on-site natural gas turbines
Size
550453 square feet of data center floor area (county parcel data)
Owner / applicant
Vantage Data Centers VA2 LLC
Decided by
Loudoun County staff (site plans and equipment yard), Virginia Department of Environmental Quality (air permit)
Loading map…
Map legend
  • Existing

Vantage's VA2 campus on Glenn Drive in Sterling is the first and only data center in Loudoun powered by on-site generation, in the words of Supervisor Koran Saines (Sterling) at an Aug. 24, 2026 town hall. Seven gas turbines run regularly next to a federal building, an auto dealership and nearby homes.[1]

The data center use was by right on the property. When Dominion told Vantage a grid connection would take years, Vantage filed a revised plan to expand its equipment yard. County staff approved it at the staff level, and that approval allowed the turbines. Saines said the Board was not told about the change.[1]

Power, generators and noise

This is what happens when data centers get ahead of the power. Misty Allen, Vantage's vice president of public policy, told the town hall the company does not expect a grid connection until 2040. Jonathan Rak, deputy director of the Virginia Department of Environmental Quality, said that when a turbine failed this summer the campus ran its diesel generators for more than 24 hours.[1]

Vantage says it has spent $15 million on noise reduction, with results of 2 to 6 decibels. County zoning staff took 132 noise readings on 22 dates. Four were over the 55 dBA limit, and the county did not count them as violations because other noise sources contributed.[1]

A 2040 connection date shows how far behind the grid already is. Every campus waiting in that queue adds to the pressure for the next substation and the next line.

Who decides

The campus was approved through by-right and staff-level processes, with no public hearing on the turbines. DEQ issues the air permit. Supervisor Saines formed a working group expected to report by the end of September 2026, and has proposed a Board initiative on generator use.[1]

Proceedings

Cases, applications, bills, filings
County land-use applicationZoning map amendment for the Vantage Data Center parcelsZMAP-2022-0007 · Board of SupervisorsDecidedPermitState air permit for Vantage Data Centers VA2 (registration 74242)No number · DEQDecided
PermitStaff-level approval of an expanded equipment yard that allowed the gas turbinesNo number · Other agencyDecided

Timeline

All proceedings · newest first
  1. NewsTown hall: Vantage says it does not expect a grid connection until 2040Vantage reported $15 million in noise work. DEQ said the campus ran diesel generators for more than 24 hours when a turbine failed.No proceedingSource →
  2. NewsSterling residents raise alarms over the off-grid data centerNo proceedingSource →
  3. FilingZoning map amendment filed for the campus parcelsCounty land-use application ZMAP-2022-0007Source →
Suggest a Timeline Entry →

Who represents this area

Koran T. Saines →Supervisor, Sterling DistrictState legislators for this area: Who's My Legislator →

Across the site

Tagged Vantage VA2, Sterling
CoverageAll 4 →
Emails show how Virginia regulators downplayed data center health concernsE&E News by POLITICO · Jul 24, 2026Data center noise, fumes create flood of complaints in Loudoun CountyWJLA 7News · Jul 23, 2026After Virginia approved a gas-powered data center without public input, residents turned to a local environmental group for answersDC News Now (via Yahoo News) · Jun 9, 2026
IssuesAll 1 →
The pauseIssue

Sources

  1. [1]Neighbors continue to raise concerns as Vantage touts $15M in data center noise mitigation efforts. Loudoun Now. Aug 25, 2026.
  2. [2]Existing data center parcels (parcel 032155119000). Loudoun County GIS. Oct 8, 2026.
  3. [3]Air permit, Vantage Data Centers VA2 LLC (registration 74242). Virginia Department of Environmental Quality. Oct 1, 2024.
Get the updates

Dates, decisions and what you can do, before each vote and hearing

Sent when something is coming up, usually a few times a month. Unsubscribe in one step.