Yondr Tarring data center
A pending special exception for a data center on about 11 acres at Youngwood Lane and Briarfield Lane in the Dulles District, next to Yondr's existing campus. A legislative application, so the Board's pause would apply.
- Type
- Data center use in the General Industry (GI) district, by special exception
- Size
- 10.96 acres (county planning correspondence)
- Owner / applicant
- Yondr (applicant)
- Decided by
- Loudoun County Planning Commission (recommendation), Loudoun County Board of Supervisors
- Proposed or under review
Yondr, which already runs a data center campus near Arcola, has applied for a special exception to build a data center on about 11 acres south of Briarfield Lane and east of Youngwood Lane, in the General Industry district.[1][2]
The application, LEGI-2025-0049, asks for the data center use plus five changes to the rules that protect neighbors:
- no berm or fence along part of the Youngwood Lane frontage
- a 100-foot setback instead of 200 feet on the south and east
- no building height limit within 400 feet of residential property
- no building step-back within 400 feet of residential property
- no Type C buffer along the northern boundary
County staff denied Yondr's request to skip the tree survey that the application checklist requires.[1]
What the new rules require
This is the kind of case the new rules were written for. Since March 2025 a data center in this district needs a special exception, with public hearings at the Planning Commission and the Board. Each of the five minor exceptions above is a request to set aside a standard written to protect homes nearby.
Where it stands
The application is in review. We have not found a Planning Commission hearing date. Because it is a legislative application, it falls under the pause the Board directed on Sept. 15, 2026: the Board would hold off on a final vote for up to 12 months from the date the application first goes to the Planning Commission, so Phase 2 rules can apply.[3]
Proceedings
Timeline
- FilingFour more minor special exceptions added to the applicationSPEX-2026-0018 to 0021: a smaller setback, no height limit and no step-back near homes, and no northern buffer.Source →
- FilingYondr files the legislative applicationSource →
- FilingYondr asks to skip the tree survey; the county later denies the requestSource →
Coming up for this item
Full Calendar →Who represents this area
Across the site
Sources
- [1]LEGI-2025-0049, Yondr-Tarring (LOLA case record). Loudoun County. Nov 10, 2025.
- [2]PCOR-2025-0059, Yondr Tarring checklist waiver (site acreage and parcel). Loudoun County. Aug 7, 2025.
- [3]Revised Action Report, Board of Supervisors Business Meeting, Item 14.l (the pause). Loudoun County. Sep 17, 2026.