Morrisville to Wishing Star

Dominion's 36.6-mile 500 kV line from Fauquier County through Prince William to the Wishing Star Substation near Arcola, with a 4.4-mile rebuild in Loudoun. SCC hearing starts Nov. 16, 2026.

Where it stands
SCC PUR-2026-00021: Hearing Examiner's Ruling on Motion to Strike

Next: SCC evidentiary hearing on Morrisville to Wishing Star begins, Nov. 16

Type
500 kV overhead transmission line (#5008), a 230 kV line and rebuilds of existing lines in the corridor
Size
36.6 miles (500 kV line, all three counties)
Owner / applicant
Dominion Energy Virginia
Decided by
State Corporation Commission
District
Dulles
Application
PUR-2026-00021
Tall steel and wood transmission poles and substation equipment behind a chain-link fence under a blue sky.
Dominion's Wishing Star substation, June 21, 2026. Photo: United Loudoun

Morrisville to Wishing Star is Dominion's second large 500 kV project reaching into Loudoun after Golden to Mars. It runs from the Morrisville Station in Fauquier County through Prince William County to the Wishing Star Station near Arcola. Dominion filed it with the SCC on Feb. 27, 2026, at an estimated $873.6 million, with a target in-service date of Dec. 31, 2030.1

The application covers a new 36.6-mile 500 kV line, a new 8.1-mile 230 kV line in Fauquier, and the rebuild of many existing lines in the same corridor. In Loudoun the work is the last 4.4 miles, from the Loudoun and Mosby stations to Wishing Star, mostly inside the existing right-of-way, with new monopoles averaging about 177 feet.

What it means for Loudoun

Dominion says the project fixes reliability violations PJM identified in its 2022 and 2024 planning cycles. Respondents from the Piedmont Environmental Council, Fauquier County and the American Battlefield Trust tie the need to data center load. The Piedmont Environmental Council's witness describes the line as the southern part of the same set of projects that loops around eastern Loudoun from Wishing Star to Mars, Mars to Golden and Golden to Aspen.

Loudoun County is a party to the case.2 So are Fauquier County, the Piedmont Environmental Council, the American Battlefield Trust, two homeowners associations, a homebuilder, and four data center land companies.

What happens next

Written comments are due by 5 p.m. on Oct. 30, 2026. The evidentiary hearing begins Nov. 16, 2026 at 10 a.m. in Richmond and may run through Nov. 24. A Hearing Examiner will then file a report with recommendations before the SCC decides.3

Loading map…
Map legend
  • Proposed or under review

Timeline

  1. Written comments due on Morrisville to Wishing StarDeadline, from the calendar Source
  2. SCC PUR-2026-00021: Hearing Examiner's Ruling on Motion to StrikePUR-2026-00021. Source
  3. SCC PUR-2026-00021: Hearing Examiner's Ruling on Virginia Electric and Power Company's Legal MemorandumPUR-2026-00021. Source
  4. Public witness hearing by phone and webcastPUR-2026-00021.2
  5. Respondents file testimonyFauquier County, the Piedmont Environmental Council, the American Battlefield Trust, two homeowners associations and a homebuilder filed direct testimony on Aug. 13 and 14.1
  6. Hearing Examiner moves the evidentiary hearing to Nov. 16Granted a six-week extension of the respondent testimony deadline. Written comments are now due Oct. 30, 2026.1
  7. Loudoun County files a notice of participationPUR-2026-00021.1
  8. SCC dockets the case and sets the schedulePUR-2026-00021.1
  9. Dominion files its applicationSeven volumes, about $873.6 million in 2025 dollars, with a target in-service date of Dec. 31, 2030.1

Suggest a timeline entry

Proceedings

  1. PUR-2026-00021Application for the 500 kV Morrisville-Wishing Star Line #5008, 230 kV Anderson Branch-Morrisville Line #2464 and expanded corridor optimizationSCC case, SCC, Open.

News coverage

Sources

  1. Virginia State Corporation Commission, “Case No. PUR-2026-00021, case details and filings,” Feb. 27, 2026
  2. Loudoun County, “Transmission line projects in Loudoun County,” Oct. 8, 2026
  3. Virginia State Corporation Commission, “Hearing Examiner's Ruling granting the motion to modify the procedural schedule,” June 29, 2026

Sign up for updates

Dates, decisions and what you can do, by email.