Yondr, which already runs a data center campus near Arcola, has applied for a special exception to build a data center on about 11 acres south of Briarfield Lane and east of Youngwood Lane, in the General Industry district.12
The application, LEGI-2025-0049, asks for the data center use plus five changes to the rules that protect neighbors:
- no berm or fence along part of the Youngwood Lane frontage
- a 100-foot setback instead of 200 feet on the south and east
- no building height limit within 400 feet of residential property
- no building step-back within 400 feet of residential property
- no Type C buffer along the northern boundary
County staff denied Yondr's request to skip the tree survey that the application checklist requires.1
What the new rules require
This is the kind of case the new rules were written for. Since March 2025 a data center in this district needs a special exception, with public hearings at the Planning Commission and the Board. Each of the five minor exceptions above is a request to set aside a standard written to protect homes nearby.
Where it stands
The application is in review. We have not found a Planning Commission hearing date. Because it is a legislative application, it falls under the pause the Board directed on Sept. 15, 2026: the Board would hold off on a final vote for up to 12 months from the date the application first goes to the Planning Commission, so Phase 2 rules can apply.3
Timeline
- Four more minor special exceptions added to the applicationSPEX-2026-0018 to 0021: a smaller setback, no height limit and no step-back near homes, and no northern buffer.1
- Yondr files the legislative applicationLEGI-2025-0049.1
- Yondr asks to skip the tree survey; the county later denies the requestPCOR-2025-0071. Source
Proceedings
- LEGI-2025-0049Yondr-Tarring: special exception for a data center and five minor special exceptionsCounty land-use application, Board of Supervisors, Pending.
- SPEX-2025-0128Special exception to permit a data center use in the GI districtCounty land-use application, Board of Supervisors, Pending.
- PCOR-2025-0071Request to waive the tree survey requirement (denied)Informal, Closed.
News coverage
Sources
- Loudoun County, “LEGI-2025-0049, Yondr-Tarring (LOLA case record),” Nov. 10, 2025
- Loudoun County, “PCOR-2025-0059, Yondr Tarring checklist waiver (site acreage and parcel),” Aug. 7, 2025
- Loudoun County, “Revised Action Report, Board of Supervisors Business Meeting, Item 14.l (the pause),” Sept. 17, 2026