The Board moved the vote up from Dec. 1. Nothing reported says the design has changed, and the full terms of the Vantage deal aren't public.
Tonight: the Board takes up data center grandfathering
In This Email:
Board of Supervisors tonight: grandfathering and audit them all
Dominion-NextEra merger: NextEra's Florida Scandal
Dominion-NextEra merger: SCC public hearing Friday in Fairfax

Do we need more?
Board of Supervisors tonight: grandfathering and audit them all
The Board of Supervisors takes up data center grandfathering tonight, Item 10.a. On Sept. 1 the Board asked for a legal opinion and a public list of every application still claiming grandfathered status. That list comes back tonight.
The list shows what is claiming grandfathered status. The ask tonight is to audit every data center project still in the pipeline and find out which ones actually have the rights they claim.
Before the meeting: email the entire Board at bos@loudoun.gov. Tell them to audit every data center project in the pipeline.
To speak: the county's sign-up page has the details.
Come out if you can: public comment starts at 6 p.m. in the Board Room of the Loudoun County Government Center, 1 Harrison St. SE, Leesburg. Wear green to show your support.
Supervisor Laura TeKrony wrote in the Loudoun Times last week about how grandfathering lets pending data center applications skip public hearings.
What the Board should do
Notice first. Staff tells the Board and the public before any action that locks in a data center's rights, early enough for people to comment.
Every project in the pipeline. An independent reviewer, if needed, checks every data center and substation application still in the pipeline, whatever its filing date or claimed status.
The vested rights questions. What county approval does each project rely on? What did it spend after that approval, beyond buying land and drawing plans? Has it actually pursued the project since? Staff verifies the answers instead of taking the applicant's word.
What has changed. Redesigns, lapsed approvals, unmet conditions, and the power lines and substations each project needs.
Public reporting. Staff reports the findings to the Board and posts them online.
Email the Board at bos@loudoun.gov before tonight and ask for these things.
What the pipeline means for Loudoun
When the county ended by-right data centers in March 2025, it let the applications already in the pipeline keep moving under the old rules. They go through staff review with no public hearing and no Board vote. The pause the Board voted toward on Sept. 15 does not reach them. The county is still writing its new data center standards and held open houses last week on noise, substations, on-site power and design.
We are surrounded by data centers, and a lot more are in the pipeline right next to them. Aspen to Golden and Golden to Mars would serve those data centers, however they are routed. But that still isn't enough. New lines like Morrisville to Wishing Star and Valley North will bring more power into Loudoun, but that power still has to get to the data centers. More lines will be needed. Nobody will tell us where the next one goes.
Everything in Loudoun that isn't a data center - every home, office, school and business - uses about 0.9 gigawatts. The conservative projection officials use has Loudoun adding 10 times that by 2030. Ten times everything else in the county, in about four years. Power lines get built to carry that load.
Every data center the county approves, or lets through without a hearing, is a vote for the next substation and the next power line. The Board said as much when it denied the Tech Park substation on Sept. 15: a substation like that promotes "new high wattage users" and "new high voltage transmission lines within the County."
Data centers do what they are allowed to do. Right now the people who live closest get no say. The lines data centers need should be paid for by the data centers, not added to residential electric bills.
The Board had a good September. It deferred the Golden Substation, voted to move toward a pause, and came out against Valley North and any new overhead power line corridor through Loudoun. Tonight it can check what is already in the pipeline. You can't be against the lines and keep approving the load.
Dominion-NextEra merger: NextEra's Florida Scandal
The SCC's chief hearing examiner ruled Friday that NextEra is compelled to turn over records about an internal investigation into whether Florida Power & Light, its Florida utility, secretly used corporate money to influence elections, target elected officials and intimidate journalists. NextEra has to produce the records this week in the Dominion merger case.
In June, NextEra agreed to pay $150 million to settle a dispute over whether it lied about its involvement in political interference schemes in Florida.
A Dominion lawyer argued that what NextEra did under its previous leadership isn't relevant because of heavy staff turnover since. The hearing examiner found the records discoverable.
The SCC will decide later what goes into the record as evidence. Brennan Gilmore, executive director of Clean Virginia, which brought the motion, said how NextEra's leadership responded to the allegations "goes directly to how it would govern Dominion."
The SCC is also weighing Attorney General Jay Jones' request to reset the clock on the case after Dominion and NextEra amended their proposal in mid-September. The current deadline for the SCC to decide is Jan. 11. If the clock resets, the case runs into the spring.
Dominion-NextEra merger: SCC public hearing Friday in Fairfax
The SCC is holding in-person public hearings on the merger in Newport News, Fairfax and Richmond.
Given Loudoun's turnout at SCC hearings, I can't believe Loudoun wasn't a stop too.
Or maybe I can.
The closest is this Friday in Fairfax.
When: Friday, Oct. 9, 6 to 8 p.m.
Where: Fairfax County Government Center, Board Auditorium, 12000 Government Center Parkway, Fairfax
To speak: no advance sign-up. Arrive at least 15 minutes early and tell SCC staff you want to testify. Two minutes per speaker.
Can't make it: testify by phone Nov. 5, 9 or 10 (sign up by Nov. 2), or submit written comments through Nov. 9 on the SCC's merger page. The case is PUR-2026-00112.
———————————————————————————
Tonight: email bos@loudoun.gov, and come out at 6 p.m. in green if you can.
Ask the Board to audit every data center project in the pipeline.
More updates
Vantage and Golden, the pause pushed to November, Amazon drops GW campus data centers, Quantum Park denied, and SCC staff on the merger