B.F. Saul wants to build a utility substation on Route 28 in Sterling, across the highway from Dominion's Global Plaza substation. The applicant's appeal says the substation will serve the data center campus proposed next door on the Dulles Technology Park site.1
What is before the Board
The Board takes this up in two parts at its Nov. 12, 2026 public hearing at 6:00 p.m.:
- Item 3.a, the appeal. The Planning Commission denied the Commission Permit for the substation on Sept. 22. The applicant appealed on Oct. 2 and is asking the Board to overrule the Commission. The Board must decide by Dec. 1, 2026. If it does not, the appeal is automatically denied.1
- Item 3.l, the rezoning and special exceptions. A rezoning of 1.69 acres from commercial to industrial park, and two special exceptions to allow a substation on the site. Action on these waits until the appeal is decided. The County Attorney's office has not approved the proffers and conditions, so staff says they are not ready for action.2
What the Planning Commission did
The Commission heard the case on Sept. 22. No members of the public spoke. It voted 4-3-1-1 to deny the Commission Permit and to recommend denial of the rezoning and special exceptions. Banks, Combs and Myers opposed, Jasper was absent and Miller abstained.1
The Commission's findings for denial:
- A substation and industrial park zoning are more industrial than the existing commercial zoning and flex buildings, which fit the county's plan for the area better.
- The proposal did not commit to a maximum height or to gas insulation, which the county plan calls for at the edge of a neighborhood area.1
What changed after the Commission vote
Two days after the vote, the applicant revised the plan:2
- The application area dropped from 24.69 acres to 10.94 acres, covering the northern three parcels only. The existing flex buildings stay.
- The plan now shows one substation on the reduced site.
- A commitment to build it as a gas-insulated substation, with the equipment enclosed in structures.
- A 75-foot setback from the road, including a 50-foot planted buffer and a 10-foot berm, plus a 15-foot screen wall on all four sides.
The plan still does not commit to a maximum height for the structures. Staff asked for that information so it can finish its compatibility review.2
What staff says
Staff can support approval with the proffers and conditions. Staff notes the county plan does not call for a substation in this area but does support needed electrical infrastructure. It asks the Board to decide whether the screening is enough, especially from Route 28, Shaw Road and Lindsay Cars Court.2
The transmission line
The appeal points to a separate Dominion project, the Global Plaza Extension: a new double-circuit 230 kV line connecting the Global Plaza substation to an existing line. The appeal says the routes Dominion is weighing cross this property, that the line is independent of the substation, and that it does not need county approval.1
Dominion expects to file the line with the SCC in early December 2026, with construction from mid-2028 to late 2029.3
Who has been heard
The applicant has held no community meetings. Staff has received no public comments on this application.1
How to weigh in
The Board's public hearing is Thursday, Nov. 12, 2026 at 6:00 p.m. in the Board Room at the Government Center in Leesburg. To speak, see the county's sign-up page, or email the Board at bos@loudoun.gov.
Written comments go on the county's Land Applications and Comments Tool. Search "LEGI-2025-0053."
Timeline
- Applicant appeals the Commission's denial to the BoardThe Board must act by Dec. 1, 2026, or the appeal is denied automatically.1
- Applicant shrinks the site and commits to a gas-insulated substationThe application area dropped from 24.69 to 10.94 acres. The plan still does not commit to a maximum height.1
- Planning Commission denies the substation permit, 4-3-1-1Banks, Combs and Myers opposed; Jasper was absent; Miller abstained. The Commission also recommended denial of the rezoning and special exceptions.1
Proceedings
- APPL-2026-0006Appeal of the Planning Commission's denial of the Commission Permit (CMPT-2025-0009)County land-use application, Board of Supervisors, Pending.
- LEGI-2025-0053Rezoning of 1.69 acres and two special exceptions for a utility substationCounty land-use application, Board of Supervisors, Pending.
News coverage
Sources
- Loudoun County, “APPL-2026-0006, LEGI-2025-0053, Dulles North Technology Park: CMPT-2025-0009, staff report and appeal, Board of Supervisors Public Hearing of Nov. 12, 2026, Item 3.a,” Nov. 12, 2026
- Loudoun County, “LEGI-2025-0053, Dulles North Technology Park, staff report, Board of Supervisors Public Hearing of Nov. 12, 2026, Item 3.l,” Nov. 12, 2026
- Dominion Energy, “Global Plaza Extension 230 kV project page,” Nov. 8, 2026