B.F. Saul, through Dulles Technology Park LLC, wants to rezone 37.24 acres on Route 28 in Sterling to build three data center buildings totaling 979,055 square feet. The site now holds an office and warehouse park. The rezoning converts it from the county's 1972 zoning to the current Industrial Park district. That is allowed in the Route 28 Tax District, but it still needs a Board vote.1
What is before the Board
The Board hears the rezoning and a request to close Holiday Drive and give the road to the developer at its Nov. 12, 2026 public hearing at 6:00 p.m. (Items 3.k and 3.m).12
The substation proposed just north of the site, which the developer says will serve these data centers, is on the same agenda. See Dulles North Technology Park Substation.
Holiday Drive
Holiday Drive (Route 1004) is a fully built public road maintained by VDOT, about 0.92 acres of right-of-way. NVA Development Corporation, a B.F. Saul subsidiary, asked the Board to abandon it and convey the land to 1000 Sully Road LLC, another B.F. Saul subsidiary, so the road land can be developed with the rest of the data center site. The abandonment is written into the rezoning's proffers.2
Staff recommends approving the abandonment only if the Board approves the rezoning.2
What the Planning Commission did
The Commission held its public hearing on May 26. No members of the public spoke. Its discussion covered building height, traffic, the substation proposed to the north, the site's location in the Route 28 Tax District, and the grandfathering resolution the Board adopted with the Phase 1 data center standards. The Commission voted 9-0 to send the case to a work session.1
After the hearing, the applicant:1
- Cut the maximum building height from 100 feet to 70 feet.
- Committed to Tier 4 generators.
- Said future data center uses will meet the Zoning Ordinance noise standards.
At its Sept. 17 work session the Commission voted 5-4 to send the case to the Board with a recommendation of denial. Banks, Combs, Miller and Myers opposed. Members discussed building design, fit with surrounding uses, whether the existing office and warehouse uses are still viable, the pattern of development along Route 28, and other uses for the site.1
What staff says
Staff supports approval and lists no outstanding issues. Staff says converting the site fits the county plan for the Route 28 corridor and that data centers would generate about 90 percent fewer weekday vehicle trips than the existing uses.1
The County Attorney's office has not approved the proffers, so staff says the application is not ready for action on Nov. 12.1
Who has been heard
The applicant has held no community meetings. Staff received three public comments online, all opposed. They cited environmental impacts, noise, higher electricity bills and the spread of data centers in Loudoun.1
How to weigh in
The Board's public hearing is Thursday, Nov. 12, 2026 at 6:00 p.m. in the Board Room at the Government Center in Leesburg. To speak, see the county's sign-up page, or email the Board at bos@loudoun.gov.
Written comments go on the county's Land Applications and Comments Tool. Search "LEGI-2024-0056."
Timeline
- Planning Commission recommends denial, 5-4Banks, Combs, Miller and Myers opposed the motion.1
- Planning Commission public hearing; sent to a work session, 9-0LEGI-2024-0056.1
Proceedings
- LEGI-2024-0056Zoning conversion of 37.24 acres to the Industrial Park district for data centersCounty land-use application, Board of Supervisors, Pending.
- RDAB-2024-0001Abandonment of Holiday Drive and conveyance of the right-of-wayBoard action, Board of Supervisors, Pending.
News coverage
Sources
- Loudoun County, “LEGI-2024-0056, Dulles Technology Park: ZMAP-2024-0018, staff report, Board of Supervisors Public Hearing of Nov. 12, 2026, Item 3.k,” Nov. 12, 2026
- Loudoun County, “RDAB-2024-0001, Proposed Abandonment of Holiday Drive and Conveyance of the Abandoned Right-of-way, staff report, Board of Supervisors Public Hearing of Nov. 12, 2026, Item 3.m,” Nov. 12, 2026