The Golden Substation is where Golden to Mars begins. Dominion plans it on the north side of the W&OD Trail near Route 28 and Pacific Boulevard in Sterling.
The SCC approves the transmission lines. The substation itself is a county land use decision. Dominion's application, LEGI-2025-0012, asks for a commission permit and three special exceptions: one for the substation use in the Industrial Park district, one to shrink or remove the required landscape buffers on all four sides, and one to cut required parking from 30 spaces to one.1
What has happened
The Planning Commission recommended approval 6-1-2 in July 2026, with members unhappy about the design. Commissioner Mark Miller (Catoctin) voted no, saying the design still looks like a 20-foot wall.3
On Sept. 1, 2026 the Board of Supervisors deferred the vote to December, 5-4, to press Dominion for a better design. Supervisor Matt Letourneau (Dulles) voted no: "We're now at a point where this is a reliability substation." Dominion told the Board the alternative designs put forward are not possible because Golden converts higher voltages than the examples shown.2
On Oct. 20, 2026 the Board voted 8-0-1, with Supervisor Juli Briskman (Algonkian) absent, to move the vote up to Nov. 5. The move came with an understanding with Dominion and Vantage to get Vantage's Sterling data center off its on-site gas turbines in 2028. Dominion said a temporary arrangement would supply part of the campus's power by the end of 2028.4
The county's vote
This is the Board's own decision, and one of the few places on Golden to Mars where the county has a vote. On Nov. 5, 2026 the Board approved it 6-3, with Chair Phyllis Randall and Supervisors Juli Briskman (Algonkian) and Laura TeKrony (Little River) opposed.5 The SCC's target in-service date for the lines is June 1, 2028.
Who decides
The Board of Supervisors votes on the special exceptions. County staff review the site plan, EPLAN-2026-0029, which is filed and in review.
- Proposed or under review
Photos


Key votes
Timeline
- Board approves the Golden Substation, 6-3Chair Randall and Supervisors Briskman and TeKrony voted no. The county Action Report is not posted yet.5
- Board of Supervisors votes on the Golden SubstationVote, from the calendar Source
- Board moves the Golden Substation vote up to Nov. 5Passed 8-0-1, with Supervisor Briskman absent. The move came with a plan to take Vantage's Sterling campus off its gas turbines by the end of 2028.4
- Board defers the Golden Substation vote to DecemberThe motion to defer passed 5-4. Supervisors Letourneau, Turner, Kershner and Umstattd voted no.2
- Planning Commission recommends approval, 6-1-2Commissioners pressed Dominion on the 20-foot wall and screening. The application went on to the Board.3
- Dominion files the site planEPLAN-2026-0029. Source
- Dominion files the land use applicationLEGI-2025-0012.1
Proceedings
- LEGI-2025-0012Golden Substation: commission permit and special exceptionsCounty land-use application, Board of Supervisors, Decided.
- SPEX-2025-0032Special exception for a utility substation in the Industrial Park districtCounty land-use application, Board of Supervisors, Decided.
- SPEX-2025-0033Minor special exception to reduce or remove required buffersCounty land-use application, Board of Supervisors, Decided.
- SPEX-2025-0137Special exception to cut required parking from 30 spaces to oneCounty land-use application, Board of Supervisors, Decided.
- CMPT-2025-0005Commission permit for a public utilityCounty land-use application, Planning Commission, Decided.
- EPLAN-2026-0029Site plan for the substationPermit, Other agency, Pending.
News coverage
From our newsletter
Sources
- Loudoun County, “LEGI-2025-0012, Golden Substation (LOLA case record),” June 4, 2025
- Loudoun Now, “Loudoun supervisors delay Golden Substation,” Sept. 2, 2026
- Loudoun Now, “Planning Commission approves plans for Golden Substation,” July 10, 2026
- Loudoun Now, “Vantage eyes earlier removal of gas turbines amid agreements with Saines, Dominion,” Oct. 21, 2026
- Loudoun Now, “After Months of Delay, Golden Substation Garners Board Approval,” Nov. 6, 2026