Issues / Valley North 765 kV line (Valley Link)

Valley North 765 kV line (Valley Link)

A 765 kV overhead line proposed across western Loudoun by Valley Link, a joint venture of Dominion, FirstEnergy and AEP's Transource. Residents in Lovettsville, Taylorstown and the Catoctin District are fighting it, and we stand with them.

Where it stands
Board of Supervisors opposes Valley North, 9-0

Next: Valley North open house in Lovettsville, Nov. 12

Type
765 kV overhead transmission line, about 260 miles in all
Size
30 miles in Virginia (Frederick, Clarke and Loudoun counties)
Owner / applicant
Valley Link Transmission, a joint venture of Dominion Energy, FirstEnergy Transmission and Transource Energy (AEP)
Decided by
State Corporation Commission (Virginia route), PJM Interconnection (selected the project)
District
Catoctin
Loading map…
Map legend
  • Proposed or under review

Valley North is a new 765 kV overhead transmission line through northwestern Loudoun, on a new cleared right-of-way about 200 feet wide, with steel lattice towers averaging about 175 feet tall.1 Routes are still being drawn. No application has been filed in Virginia, West Virginia or Maryland.3

Next open houses

Valley Link is showing revised route options this month. These sessions shape which route the company files. Go, look at the maps, and leave written feedback. Turnout is counted.4

  • Thursday, Nov. 12, 2026, 4 to 7 p.m. - Lovettsville Game Protective Association, 16 S. Berlin Pike, Lovettsville
  • Thursday, Nov. 19, 2026, 4 to 7 p.m. - Brunswick Fire Hall, 1500 Volunteer Drive, Brunswick, Md. Same maps and format, about eight miles from Lovettsville.

Both are drop-in. There is no formal presentation.

How to comment and what to say

What we are asking for

  • No new overhead greenfield corridor through western Loudoun. The Board of Supervisors took this position on Sept. 15, and we agree with it.1
  • A real study of underground HVDC and of existing corridors before any route is chosen. Virginia law lets the county require the SCC to consider underground placement.1
  • Hold Valley Link to the state's new standard. Since July 1, 2026, the SCC must favor routes for lines of 500 kV or more whose center is more than 150 feet from homes, schools, day cares and places of worship.1
  • Protect the conservation easements the county and Virginia paid for.
  • The customers who need this power pay for the infrastructure that serves them, not the families in the way.

Why it is here

Nothing in western Loudoun needs a 765 kV line. The line exists to move power east, to the data centers already approved and the ones still in the pipeline. The farms, towns and conservation land in between get the towers. They got none of the data centers.

That is the pattern across the county. Dominion has a plan. The data centers have a plan. Loudoun and Virginia do not. Every approval in the east sends the bill west, and to Sterling, and to Ashburn, in the form of lines and substations nobody voted on.

What is at stake

  • Homes and working farms across the Catoctin District
  • The Town of Lovettsville, its historic district, community park and elementary school
  • The Taylorstown Historic District
  • Land under open-space and conservation easements, Agricultural and Forestal Districts, and land in the county's land-use program
  • Catoctin Creek State Scenic River, Sweet Run State Park and the Appalachian Trail1

Everything in the path

The people fighting it

Block Valley Link North is the group of western Loudoun neighbors leading this fight. They have organized landowners, turned people out to every open house, spoken at the Board, and built a coalition that runs from the Town of Lovettsville to both county party committees. They are doing exactly what residents should do when a project like this lands on them, and they are doing it early, before the route is locked in.

United Loudoun supports them fully. If you live in western Loudoun, join them. If you live anywhere else in the county, back them up. Every district has its own line, substation or data center fight, and none of us wins alone.

Who represents the area

  • Supervisor: Caleb Kershner, Catoctin District
  • Delegate: John McAuliff, House District 302
  • Senator: Russet Perry, Senate District 312

Key votes

Timeline

  1. Board of Supervisors opposes Valley North, 9-0The resolution opposes any new overhead transmission right-of-way through Loudoun, directs the County Attorney to join the SCC case once it is filed, and asks the SCC to hold a hearing in Loudoun.5
  2. Valley Link holds its Loudoun open house in Lovettsville7
  3. Valley Link announces the project and publishes study segments6
  4. PJM selects the Valley Link projects5

Suggest a timeline entry

Proceedings

  1. No numberPJM selects the Valley Link projects in its 2024 Regional Transmission Expansion Plan windowPJM / FERC, PJM, Decided.
  2. No numberBoard of Supervisors resolution opposing the Valley North line as proposedBoard action, Board of Supervisors, Decided.

News coverage

All 14 stories

From our newsletter

Sources

  1. Loudoun County, “Board Member Initiative and Resolution Opposing the Valley North 765 kV Transmission Line, Board of Supervisors Business Meeting of Sept. 15, 2026, Item 14.m,” Sept. 15, 2026
  2. Block Valley Link North, “home page,” Nov. 8, 2026
  3. Block Valley Link North, “Where We Stand (citing Valley Link's published schedule),” Nov. 8, 2026
  4. Block Valley Link North, “Take Action,” Nov. 8, 2026
  5. Loudoun County, “Loudoun Board opposes Valley North transmission line, denies substation near Dulles Airport,” Sept. 18, 2026
  6. Valley Link Transmission Company, “Valley North project page,” June 9, 2026
  7. Loudoun County, “Transmission line projects in Loudoun County,” Oct. 8, 2026

Sign up for updates