Amazon bought George Washington University's Ashburn campus for $427 million and filed a site plan for data center buildings there. On Oct. 20, 2026 the county announced Amazon will drop its data center plans and donate 25 acres to the county.
Issues
What we are asking officials to do, and by when.
Right nowValley North open house in Lovettsville, Nov. 12Board public hearing: Dulles Technology Park, its substation, and a noise rule, Nov. 12SCC evidentiary hearing on Morrisville to Wishing Star begins, Nov. 16
- Existing
- Proposed or under review
- Golden to Mars: Route 3A (approved June 29, 2026)
- Operating
- Under construction
- Proposed
- AWS on the former GW campus (Bridgefield Tech Center)
- Dominion and NextEra merger
- Dulles North Technology Park Substation
- Dulles Technology Park
- Golden to Mars
- Golden Substation
- Morrisville to Wishing Star
- Shreveport South data centers and the Deimos Substation
- Valley North 765 kV line (Valley Link)
- Vantage VA2, Sterling
- Yondr Tarring data center
What this map shows: Each tracked item is drawn at its site or along its route, with routes that were proposed but not chosen shown dashed. Locations marked approximate are not survey-accurate.
Data as ofAll tracked items
NextEra Energy's proposed acquisition of Dominion Energy, Loudoun's electric utility, before the SCC as PUR-2026-00112. Public witness hearings Nov. 5, 9 and 10; evidentiary hearing from Nov. 17, 2026.
A substation for a proposed data center campus on Route 28 in Sterling. The Planning Commission denied it. The applicant appealed, and the Board must decide by Dec. 1, 2026.
Three data center buildings, about 979,000 square feet, on 37 acres off Route 28 in Sterling, plus the handover of a public road to the developer. The Planning Commission recommended denial. Staff supports it.
Dominion's 500 kV and 230 kV lines between the Golden and Mars substations in eastern Loudoun. The SCC approved Route 3A on June 29, 2026, and the decision is on appeal.
Dominion's 500 kV substation near Route 28, Pacific Boulevard and the W&OD Trail in Sterling, where Golden to Mars begins. The Board approved it Nov. 5, 2026, 6-3.
Dominion's 36.6-mile 500 kV line from Fauquier County through Prince William to the Wishing Star Substation near Arcola, with a 4.4-mile rebuild in Loudoun. SCC hearing starts Nov. 16, 2026.
STACK Infrastructure plans 1.3 million square feet of data centers 265 feet from homes on Evergreen Mills Road. NOVEC's Deimos Substation would power them, and it needs a Board vote.
A 765 kV overhead line proposed across western Loudoun by Valley Link, a joint venture of Dominion, FirstEnergy and AEP's Transource. Residents in Lovettsville, Taylorstown and the Catoctin District are fighting it, and we stand with them.
A Vantage Data Centers campus on Glenn Drive in Sterling that runs on on-site gas turbines because the grid cannot yet serve it. Vantage says it does not expect a grid connection until 2040.
A pending special exception for a data center on about 11 acres at Youngwood Lane and Briarfield Lane in the Dulles District, next to Yondr's existing campus. A legislative application, so the Board's pause would apply.